Jeddah Tower reaches 120 floors at about 482 metres

Kingdom Holding reported that Jeddah Tower in Jeddah has reached 120 floors and roughly 482 metres, with more than 322,000 cubic metres of concrete poured and over 3,900 façade panels installed.

ARTIFEXNews desk, Madinah

Published
Place
Jeddah
Topic
Construction
Reading time
2 min
Jeddah Tower reaches 120 floors at about 482 metres

StatusProgress figures are Kingdom Holding's own; the wider study is a press release from an independent UK publication.

Kingdom Holding reported on 2 November 2026 that Jeddah Tower had reached 120 floors and approximately 482 metres. More than 322,000 cubic metres of concrete had been poured and over 3,900 façade panels installed. Mechanical, electrical and plumbing work were also advancing.

The project is being developed by Jeddah Economic Company, with Saudi Binladin Group undertaking the main construction works. The tower was designed by Adrian Smith + Gordon Gill Architecture, with Thornton Tomasetti as structural engineer. Its planned height is more than one kilometre, and completion is forecast for 2028, subject to the remaining delivery programme.

The tower presents a demanding test of wind engineering, concrete placement, vertical transport and complex high-level logistics. It anchors the wider Jeddah Economic City development reinforces the city's appeal to international developers, engineers, specialist contractors and investors.

Kingdom Holding announced a SAR 7.2 billion agreement for the tower's remaining construction works in October 2024. The source stresses this is an important project-level contract value, not a measure of the city's total investment. It adds that opportunities still require careful assessment of commercial, regulatory and delivery risks.

The progress was highlighted in the study Global Tall Building Construction 2027: Ten Cities to Watch, published on 4 November 2026. The independent UK publication features Jeddah among ten cities across ten countries. The study is not a numerical ranking; it distinguishes live construction, topped-out projects and proposals, using records available up to 3 November 2026.

The publication's founder and editor said: "Jeddah is showing the world what engineering ambition looks like. A building designed to rise beyond one kilometre demands extraordinary technical skill, coordination and determination." He added that the progress places Jeddah firmly on the global construction map.

Key figures

  1. 120floors
  2. 482 m≈ height reached
  3. 322,000+m³ concrete poured
  4. 3,900+façade panels installed
  5. SAR 7.2bnremaining-works agreement (October 2024)
  6. 1km+ planned height
  7. completion forecast 2028