Infrastructure

Saudi Arabia expands desalination and sewage treatment PPP pipeline

Saudi Arabia is nearly doubling its procured desalination capacity by 2031 and lifting sewage treatment coverage through PPP plants, with SHARAKAT as the main buyer and more than 50 developers prequalified.

ARTIFEXNews desk, Madinah

Published
Place
Saudi Arabia
Topic
Engineering
Reading time
3 min
Saudi Arabia expands desalination and sewage treatment PPP pipeline

StatusAnalysis of published programme figures; targets are plans, not completed capacity.

Saudi Arabia is the world's largest desalination market, and as it works towards its National Water Strategy 2030 targets it continues to offer a large number of public-private partnership (PPP) opportunities for developers. A parallel programme is under way to expand sewage treatment. As with desalination, much of the new capacity falls under SHARAKAT, described as the principal buyer of all types of water in the kingdom.

Urban water demand stands at 263 litres per capita per day, well above the global average, driven by population and GDP growth and highly competitive tariffs. Desalination supplies 79% of urban water requirements. As natural aquifers are protected, the aim by 2030 is for all regions except Najran, Hail, Al-Jawf and the Northern Borders to rely on desalinated supply rather than groundwater.

Over two decades SHARAKAT has procured nine independent water plants (IWPs) across the Eastern Province, Western Region and Jizan Region. Its portfolio is projected to almost double from 3.88 million cm/d in 2025 to 7.18 million cm/d by 2031. Two IWPs are under construction: Rabigh 4 at 600,000 cm/d, targeted for commercial operation in 2026 and awarded to a consortium led by Acwa with Haji Abdullah Alireza Company (HAACO) and Al-Moayyed Contracting Group.

Ras Mohaisen Phase 1, at 100,000 cm/d, is targeted for 2028, followed by a second phase adding 200,000 cm/d in 2030. Acwa, HAACO and AlKifah Holding are developing and operating it. Four further IWPs, Shuqaiq 4, Ras Al-Khair 3, Tabuk 1 and Ras Al-Khair 2, are scheduled to start procurement over the next 18 months, and all have completed the expression of interest stage.

SHARAKAT's prequalification programme lets developers and contractors join upcoming water and wastewater PPP projects without a separate qualification application each time. More than 50 local, regional and international developers are now prequalified. The programme accepts new applicants every quarter, with updates announced through SHARAKAT's official social media channels.

The National Water Strategy targets 10 million cm/d of treatment capacity by 2030 and reuse of 70% of all produced water, aiming for a circular water economy. Treatment coverage has grown from 56.7% in 2019 to 64% in 2025, largely through new independent sewage treatment plants (ISTPs). Ten ISTPs are operational, under construction or in tendering, with combined capacity of 1.79 million cm/d, expected to reach 3.19 million cm/d after identified expansions.

Dammam West ISTP, the first ISTP PPP, has 200,000 cm/d capacity expandable to 350,000 cm/d, and Jeddah Airport 2 has 300,000 cm/d expandable to 500,000 cm/d. Three projects are in active procurement. Two are named: Hadda ISTP at 100,000 cm/d, expandable to 250,000, with a Metito-led consortium including EtihadWE and SkyBridge Company; and Arana ISTP at 250,000 cm/d, expandable to 500,000, led by Miahona, Marafiq and Buhur for Investment Company.

Key figures

  1. 3.88mcm/d portfolio 2025
  2. 7.18mcm/d portfolio by 2031
  3. 263LCD urban demand
  4. 79%desalination share
  5. 64%treatment coverage 2025
  6. 10mcm/d treatment target 2030
  7. 70%reuse goal
  8. 1.79mcm/d ISTP capacity